1. Networking

  1. Power cycle the ONT. Wait until the top three lights are green.
  2. Power cycle the modem. Wait until the power, WAN, and Ethernet 1 lights are green.
  3. Power cycle the router Switches and APs should not need power cycling. Once the indicator LED is solid white, everything should be back online.

2. Homelab

  1. Power on the desktop or laptop.
  2. Power on the NAS. The DS4243 will power itself on automatically. Wait until the webui at nas.jafner.net is responsive.
  3. Power on the Server. Once it is accessible, run a sudo mount -a to mount all network shares defined in /etc/fstab. Then run docker start $(docker ps -aq) to start all Docker containers. Note: Run docker inspect -f '{{ .Mounts }}' $(docker ps -q) to get a list of volumes for all running containers, useful for determining whether a container is reliant on a mounted directory.